T2
Architect's Diary |
|
Friday, May 20, 2005
Sold
The Terrace was sold this week. Monday, May 16, 2005
Finished
The works are finally complete. Monday, March 28, 2005
Finishing 8
The rear seat and screen feature is now complete and the shower screen for the ensuite has been installed. Thursday, March 24, 2005
Rear yard works
The works to the rear yard are approaching completion. The bluestone slabs have been set on the blockwork seat bases; the feature wall behind has been painted; the lighting and lathe panel should be completed by the end of the day. (We put aside a number of the original bluestone window sills and thresholds, as well as a beautifully intact panel of lathe - the thin timber strips used to support the early plasterwork - at the beginning of the project to create this feature setting). Tuesday, March 22, 2005
Finishing 7
The builder laid the screed to the rear yard on Tuesday last week and tiling began once it had cured. Friday, March 11, 2005
Glass balustrades
The toughened glass balustrades arrived today and have been quickly installed. The uninterrupted view from the lounge through to the living, kitchen and rear, greatly enhances the quality and expanse of the space. Thursday, March 10, 2005
Water Feature
A number of the team are back on site today. Tuesday, March 08, 2005
Furniture
While there are still quite a number of outstanding and unsatisfactorily completed items, we advised the builder of Archicentre's intent to take possession of the property as of today. This has a number of contractual and legal implications but basically allows Archicentre to begin using the Terrace for its promotional purposes(together with T1 which is apparently far more complete and scheduled for auction soon). Thursday, March 03, 2005
Timber floors polished
The builder applied the finish to the timber floors before most of the crew left for a wedding in the Western District. Nothing major will be happening on site until they return early to mid week next week. Monday, February 28, 2005
Finishing 6
Carpet layer arrive this morning. We are only laying carpet in the bedrooms both upstairs and down, whereas we have used either polished timber boards or tiles in the living and trafficable areas. Tuesday, February 22, 2005
Finishing 5
Work is progressing slowly, too slowly. Thursday, February 17, 2005
Finishing 4
The rest of the joinery has finally arrived. Units are being installed in the lounge, front ground floor bedroom, upstairs bedrooms and ensuite. The shell is beginning to look complete. Wednesday, February 16, 2005
Finishing 3
Ensuite wall and floor tiling is complete with the exception of the mosaic tiling around the vanity basin. Tiling still must be grouted and cleaned. Monday, February 14, 2005
Finishing Trades 2
As the completion deadline draws ever nearer, I had expected more activity on site since my last visit than appears to have occurred. Friday, February 11, 2005
Finishing Trades 1
The laminate bedroom and bathroom joinery has begun to arrive and will be progressively installed and the solid Laminex Freestyle vanity tops and chimney shelves have been installed. We have selected Laminex for all the joinery taking full advantage of their extensive range of colours, textures and special finishes. Wednesday, February 09, 2005
Tiling
The site has been very busy this week. Tiling began Monday and will continue all week - this will be completed by Friday or Monday at the very latest. Thursday, January 27, 2005
Water Tank
Tuesday, January 18, 2005
Electrical fit off
Finishing trades are gradually returning to work after the Christmas shut-down. The painter has been in on and off over the last few weeks but cannot complete the outside painting until the renderer comes back to tidy up. Internally the timber skirting ducts and other odd bits of trims and wall tiling will need to be completed before the painter can finish off here. Monday, January 10, 2005
Kitchen Joinery
Cabinet maker began installing kitchen joinery just before Christmas. Some of the upstairs joinery units have also been delivered but are not yet in place. Have asked the builder to ensure that the joinery be protected against impact damage, scratching or marking until all works are completed and the works handed over to the client. Monday, December 20, 2004
Christmas Shutdown
Not too much will be happening over the next few weeks as the industry winds down over the Christmas break. Tuesday, December 14, 2004
Finishing off 1
The timber flooring is down and protected under a layer of thick plastic. Wednesday, December 08, 2004
External Works
Builder has started on the restoration of the front facade. The paint has been stripped from the brick capping of the fence and the window sills to reveal their natural finish - red brick and bluestone respectively. The verandah roof sheeting has been replaced with corrugated iron to match the original curve. This will be painted in its original colour. So far only the undercoat has been applied to the brickwork. Monday, November 29, 2004
Flooring
The battens have been laid over the concrete to support the timber flooring. Builder will begin laying the boards once all the electrical changes have been made and access for the services is no longer required. Wednesday, November 24, 2004
Site Meeting
Progress of work is picking up again. Thursday, November 18, 2004
Fireplaces
Instructed builder on the details of the two Jetmaster fireplaces. It is not possible to install a gas log fire as it requires a chimney cowl which will affect the appearance of the chimney and hence contravene the Planning permit. Instead we have selected a modern inset wood burner for the lounge room and a traditional Victorian Style coal fire for the front bedroom. Wednesday, November 17, 2004
Skylight
Plumber is beginning to fit off fixtures. With the bath in place, the watershield plasterboard - 'wet' tiling underlay - can be fixed and plasterwork completed. Thursday, November 11, 2004
Light Fittings
Instructed the builder on the final selection of lights. Provided a very detailed list of fittings that can be purchased from a number of nominated suppliers. Wednesday, November 10, 2004
Flooring delivered
Hardwood for the floor and the stair treads arrived at site today. Friday, November 05, 2004
Fill in time
Even with the skies clearing, after a fortnight of needed rain, the renderers now have a significant backlog of other project work that must be dealt with before they can get around to the Terraces. Our project waits in the queue. Friday, October 29, 2004
Little progress
These last few days of rain have caused a minor upset. While the rest of Melbourne and Victoria is glad to see the rain, and more of it, the construction industry is cursing. The builder had scheduled to begin rendering the external cladding and begin works to the rear yard - will have to wait for sunny skies. Monday, October 25, 2004
Lack of Progress
There appears to be little activity on site this week. Thursday, October 21, 2004
Plaster progress
Plasterboard work is in the main complete excepting a few areas where fittings windowes or skylights need to be installed before work can be finished. Repair of hard plaster to original walls of front bedroom and lounge on the ground floor has yet to be scheduled. Monday, October 18, 2004
Site Meeting
Site meeting today. Internally plasterwork is nearly finished. The work around the brickwork of the chimney is very good, further highlighting the interesting form of this feature. Wednesday, October 13, 2004
Stairs
Fabricated steel stair structure was delivered and fixed in place. It is a striking piece of sculpture, but not much practical use until the stair treads are installed. However, being able to walk hands free up and down stairs, rather than a ladder, will make the tradesmen's lives much easier. Monday, October 11, 2004
Insulation
Acoustic insulation to the floor and the remaining thermal wall insulation is in place. Tuesday, October 05, 2004
Plasterwork
Site meeting. Discussed in some detail the layout of the features in the rear garden and also the water feature in the lightwell. The chimney sweep has cleaned the flues. Wednesday, September 29, 2004
Glazing in
Attended site meeting. Progress is slow! After a chat with the electrician the down lights in the ensuite were moved to the flat area of the ceiling because the electrician considered that the transformers may get too hot under the thin front section of the roof. Saturday, September 25, 2004
Damp Proof Repairs
The damp proof work is complete, with final repairs to the hard plaster with a waterproof hard plaster mix. Wednesday, September 22, 2004
Site Meeting
Attended weekly formal site meeting this morning. Decided to build bulkhead across the sidewall of the light well to conceal the stormwater pipe that will run from the south side of the light well to the north side to connect to the other downpipe - collecting the roof rainwater for storage in the rear water tank. We can then fit downlights to the underside of this bulkhead to illuminate the water feature on the wall below. Tuesday, September 21, 2004
Hydronic Heating Rough-in
The hydronic heating rough-in is in progress. Small diameter copper pipes, lagged in thick, insulating, flexible foam material, are being threaded through the posi-struts between the ground and first floor to serve the upper level - popping up through the flooring where required. On the ground level they run either through the framing and joinery or will be concealed behind the skirting boards. The panels will be fitted off later in the project during the fit-out stage. Tuesday, September 14, 2004
Windows 2
Excepting the larger north facing windows/doors, all of the windows have been installed. Saturday, September 11, 2004
Thursday, September 09, 2004
Plasterboard Linings 1
Had a very productive meeting with the Lafarge Plasterboard representative, determining which internal spaces would benefit from using their Soundshield acoustic board as opposed to their normal internal plasterboard as well as Watershield for wet area linings. Lafarge will also be involved in the quality control of the finished fixed product and workmanship. Wednesday, September 08, 2004
Site Meeting
Fine day though overcast. Luckily with the roof now on, the weather is not so critical to work on the site. Monday, September 06, 2004
Party Wall
Just back from a few days holiday. Met on site with builder this morning to review progress and discuss details and construction program. Thursday, September 02, 2004
Framing 3
Framing to bed head recess window feature in the rear bedroom was fabricated on site and is ready for fitting into steel framed recess. Wednesday, September 01, 2004
Services Rough In
Tuesday, August 31, 2004
Roofing
Monday, August 30, 2004
Friday, August 27, 2004
On site discussions
Met the Builder on site and worked out a method of running storm water from central part of roof through the light well and the framing structure through to the rainwater tank at the rear. Tuesday, August 24, 2004
Roof Framing 2
T2 roof from above Electrical rough in has begun. Roof framing is complete. We have spent the last few weeks reviewing the various sustainability options we have proposed for T2. It is a most interesting exercise, as new products, technical information and systems are continuously being introduced to the market place in obvious response to government legislation and the public's interest. We have been investigating various water saving or conservation options in view of recent relevant studies and reports, so that we can finalise our plumbing rough in and fixture selections. There are a myriad of design issues to consider:
Using new information on the relationship between catchment area, storage tank capacity and usage rates, we have redesigned our roof drainage system to allow water to be collected over the whole of the new roof, rather than over half as previously designed. The plumbing is a more complex, but it will greatly increase the supply reliability of the tank water to flush the toilets. Monday, August 23, 2004
Damp Proof Repairs
Wednesday, August 18, 2004
Roof Framing 1
Thursday, August 12, 2004
Window Selection 2
The windows representative called into the office today with samples of the window hardware. We finalised the window schedule. They have a number of different timber species available for their frames, and we have selected a finger jointed treated pine because it best meets our sustainability objectives in this project, being a local renewable plantation timber. Wednesday, August 11, 2004
Chimney Bonus
Monday, August 09, 2004
Raising Boundary Wall
Thursday, August 05, 2004
Integrated wiring
Rained most of the day - little activity possible on site. Wednesday, August 04, 2004
Sanitary fixtures
Investigating the detailed selection of water saving sanitary and tapware for the terrace. Very interested in a soon-to-be released cistern which uses only 3 litres for a half flush and 4.5 litres for the full. Monday, August 02, 2004
Weekly site meeting
Had our regular weekly site meeting with the builder this morning. He needs our revised window details urgently. Discussed the project’s internal cladding requirements. Sound transmission between spaces is a serious project consideration and I've asked the builder to price for the use of Lafarge Soundshield plasterboard for the internal linings. Also discussed possible cabinet makers for the joinery. Will confirm list with builder and he will arrange quotes. Friday, July 30, 2004
Winter 'flu blues
Friday, July 23, 2004
Floor Structure 2
Builder has framed up the grounf level ceiling / first level floor using an open web system generically termed posi-struts. This system is lightweight and therefore easier to install that solid timber joists and the open web structure creates natural openings for ducts, pipes and other services to be threaded through. Thursday, July 22, 2004
Window Selection
Visited Canterbury Windows in Springvale with one of my architectural team. One of the sales staff took us through the showroom where we could see the examples of the range of window types in their finished form. We were then shown around the plant by the Southern Regional Sales Manager where we discussed the various types of frames in production and aspects of their manufacturing technique. Back in the office we are revising our window schedule on the basis of site measurements and Canterbury's standard details and hardware to simplify the manufacturing process. Wednesday, July 21, 2004
Blockwork 3 - rising
Overcast but fine today. Tuesday, July 20, 2004
Floor Structure 1
Further good progress with the first floor posistruts being installed. These are engineered composite beams supporting the first floor and ceiling of the ground floor. Monday, July 19, 2004
Wall Plates to First Floor
Clear weather. Wednesday, July 14, 2004
Blockwork 2
Beautiful sunshine. Friday, July 09, 2004
Slab curing
Slab is curing and is now dry enough to walk on, but not enough to work off. Brickies will start constructing common dividing wall from T1's side where the slab is at least a week older and cured. Wednesday, July 07, 2004
Slab pour
Cold and fine in the morning, still cold and rain later in day. Not the best day to be out and about! Tuesday, July 06, 2004
Slab Preparation 2
Inspection at site about 11am. I discovered that the plastic membrane had not been properly installed at the perimeters of the slab, which would have left the unprotected edges of the slab in contact with the existing and just completed new walls. This could have led to serious moisture problems in the future. Monday, July 05, 2004
Slab preparation
Rain on and off most of the day. Friday, July 02, 2004
Friday, June 25, 2004
Blockwork
Base courses of common blockwork dividing wall have been laid. Builder is investigating rectification works to remaining original walls in preparation for the new concrete floor slab. Thursday, June 24, 2004
Site Meeting
Light showers in morning. Fine in afternoon. Wednesday, June 23, 2004
Site Meeting
Freezing cold day. Monday, June 21, 2004
Structure revealed!
Builder removed the flooring and ceiling from the front room in preparation of the rectification works and new concrete slab floor. Thursday, June 17, 2004
Sub-ground Services
Sewerage drains laid and trenches backfilled. Wednesday, June 16, 2004
Old Lathe Wall
The old lathe wall was delivered to our place for storage until it is restored. We will re-use it as a feature in the rear garden. Tuesday, June 15, 2004
Plumbing work begins
The long weekend was very welcome. There has been a lot of pressure at our office with our own major renovations just commencing. Even architects are not immune to the disruption!! Wednesday, June 09, 2004
Demolition Day 4
Rain most of the day - little activity on site. Tuesday, June 08, 2004
Demolition Day 3
Weather: clear and sunny Monday, June 07, 2004
Demolition Day 2
Demolition almost complete. Large amount of dust generated. Had to keep front door closed to prevent dust billowing into street. Asked builder to use water spray to keep dust levels down. Friday, June 04, 2004
Lane Closure
Demolition begins Thursday, June 03, 2004
Power for Demolition
Have asked the client to organise power on site ASAP. Builder needs to use power hand tools to make site safe after major demolition. Wednesday, June 02, 2004
Council Documents
Need to arrange for the client to forward a letter to the City of Melbourne's planning office authorising the Builder, on their behalf, to collect copies of whatever existing services plans are needed to get the works going. Tuesday, June 01, 2004
|