Friday, October 29, 2004
Little progress

These last few days of rain have caused a minor upset. While the rest of Melbourne and Victoria is glad to see the rain, and more of it, the construction industry is cursing. The builder had scheduled to begin rendering the external cladding and begin works to the rear yard - will have to wait for sunny skies.

The stair manufacturer has yet to rectify the problems with the stair frame: several corner and newel posts are not vertical and must be fixed before the timber treads and balustrade glazing panels can be installed.

Some minor problems with the exterior cladding corner joints and trims also require rectification before jointing tape and finish can be applied.