Site Meeting

Attended weekly formal site meeting this morning. Decided to build bulkhead across the sidewall of the light well to conceal the stormwater pipe that will run from the south side of the light well to the north side to connect to the other downpipe - collecting the roof rainwater for storage in the rear water tank. We can then fit downlights to the underside of this bulkhead to illuminate the water feature on the wall below.


Rainwater collection pipes along
boundary fenceline through lightwell


Rear bifold window to Living area has been fitted. Glazing will be installed shortly. These can be opened up across the width giving the builder complete access as well as a degree of after hours security and weather protection when closed.


Rear window wall

Internal wall and floor (acoustic) insulation will be fitted this coming week prior to internal plasterwork.

Builder has requested a schedule of the heating panel sizes.