T1
Architect's Diary |
|
Tuesday, March 15, 2005
Calm
The peace and quiet of a job complete. Monday, March 07, 2005
Furnishing
The cabinetmaker began installing the final kitchen benchtops last Friday, only to find that one of them did not have the required bevelled edge treatment on both sides. Further frustrations as this one had to be sent back yet again for rectification. It arrived back here this morning but plumber must make an extra trip to fit in sinks and tapware. Thursday, March 03, 2005
Finishing 5
Front door is complete with the final fitting off of the brass letter slot. Monday, February 28, 2005
Finishing 4
The solar hot water service has finally been installed on the roof and the system connected. While it is easy to overlook as it is usually neither a main building or design element, it is imperative to check whether Planning permission is required for the installation of the roof mounted panels right from the start of a project. In our case the solar panels formed an integral part of our design and as such were included within the original Planning approval. Monday, February 21, 2005
Finishing 3
Landscape contractors arrived to complete the rear yard. They have selected mondo grass (Ophiopogon japonicus) to fill the gaps between the paving. It is not actually a grass but a lily; a low growing, spreading, evergreen perennial noted for its grass-like short, dark, glossy green leaves. It is very hardy, needs no mowing as it only grows to about 75mm (3") tall and will tolerate very dry conditions - ideal solution to softening the edges of the hard landscaping. There will be some larger 'matching' plants strategically located along the boundaries. Wednesday, February 16, 2005
Finishing 2
With the internal works almost completed, the floors are ready for polishing. The boards were sanded last night and this morning the first coat of finish is being applied. When dry, the floor will be lightly resanded and a second coat applied: all in all three coats will be applied. The finish brings out the depth of colour and lustre of the rose gum timber. Monday, February 14, 2005
Finishing 1
Extreme activity continues on site today with the builder putting a significant effort into coordinating the finishing trades and activities. Friday, February 11, 2005
Tiling Complete
The works are rapidly pulling together. Wednesday, February 09, 2005
Count Down to Practical Completion
The tiler has almost completed laying internal wall and floor tiles. Final contrast tiles to the shower shelf, external tiling and grouting will finish off this trade next week. Monday, February 07, 2005
Two weeks to go
There has been a flurry of activity at thee site over the last week and the builder assures me this will continue in order to meet the completion deadline. Friday, January 28, 2005
Study takes shape
The glass floor panel has been delivered and installed. . Monday, January 17, 2005
January Start-up
Activity on site should begin to pick up from this week on as tradesmen and suppliers begin returning from the Christmas break. Monday, January 10, 2005
New Year Activity
As expected, little has happened over the Christmas New Year period. Monday, December 20, 2004
Slow down to Christmas
While work is generally slowing down in the lead up to the new year, the builder is tidying up and finishing off the odds and ends. Tuesday, December 14, 2004
Stairs
Our stairs are finally taking shape, but we have had to move to Plan B to get them moving. Originally the stairs were included as a monetary allowance in the contract, after preliminary discussions with a specialist stair manufacturer and their cost estimate. However, after a lengthy period of negotiations between the builder, a specialist stair builder and ourselves, where the costs rose higher than the stair run, we had to instruct the builder to adopt plan B. Plan B requires the builder to coordinate the construction of the component parts; steel frame, treads, balustrade, balustrade infill panels etc rather than involving the specialist sub-contractor. In this instance it will be a significant savings in costs, though why Plan A costs escalated so far in the first place is still a mystery. Tuesday, December 07, 2004
External rendering
Missing windows have finally arrived. Monday, November 29, 2004
Progressive windows 2
Tuesday, November 23, 2004
Progressive window installation
Wednesday, November 17, 2004
Internal joinery and Windows
The joinery fitout has begun with a wall of shelves being installed in the Walk-in-Robe to Bedroom 2 and the cupboards to Bedroom 1. Several smaller units for the bathrooms and small upstairs study area are also in place. Monday, November 08, 2004
External works
The small screen fence, behind which all the unsightly services (hydronic boiler) and rubbish bins will be hidden, has been constructed. It repeats the same timber slatted screen element as in the privacy screen on the verandah above. The blueboard cement sheet will be rendered to match the rear facade when finished. Tuesday, October 26, 2004
Flooring
The lack of windows is resulting in atypical site progress. Applying some lateral thinking, the builder is tackling a number of external items first in order to keep the project moving forward. The water feature pond has been formed. The rear fence, the fence between the two Terraces and the screen fence around the small service 'yard' (more like a corner) are in progress. Monday, October 18, 2004
Plastering 2
Plastering is continuing. Forming around skylights, internal openings, windows and recesses. Plaster is a very flexible material which can be used effectively at the intersection of irregular planes to form complex shapes and angles, and to create drama and visual interest. Wednesday, October 13, 2004
Plastering 1
Builder is still waiting for the windows but is managing to keep the project moving forward. Tuesday, October 05, 2004
Plywood ceiling
With the services rough-in completed, the builder has begun fixing the plywood ceiling. However, without the weather protection of the windows, only sections of the internal linings can be fixed. The ply is weatherproof and can be used both internally and externally, allowing us to create a seamless ceiling line from the living area through to the balcony, and we hand selected the ceiling panels for colour, grain and character. Thursday, September 30, 2004
Hydronic Heating
Foster heating have roughed-in the heating pipes to each individual panel. The fit-off, or installation of the panels, will not occur until much later when all internal walls, flooring and even probably the painting has been completed. There is quite a range of different panel types and sizes to suit every application and design criteria. We are considering placing two tall narrow panels at the northern end of the living area, turning them into a definite design element, depending on availability within our construction program. Monday, September 27, 2004
Solar hot water 1
Plumber has started rough-in for connection to the roof mounted solar panel. All the pipes (even the cold water supply) must be insulated to prevent contact with the other services and the metal roofing as well as to maintain the temperature. Outlet pipes from the hot water service are now duplicated as the temperature of the water to bathroom fittings is reduced to prevent accidental burns injuries. Wednesday, September 22, 2004
Verandah Lining
Monday, September 20, 2004
Issues
Despite our best intentions, we are unable to locate the boiler for the hydronic heating system in the roof space above the front bedroom. The boiler's flue cannot be angled, but must rise vertically from the unit. This means that it would penetrate the existing roof and contravene the Planning Permit. Instead, we will place it in the back yard, behind the screen panel we originally designed to shield the water tank (which is now located in the roof space) from view.
Front Window
Took our partial sample 'heritage' profile window down to the planner at the City of Melbourne to discuss the option of replacement the front bedroom window. This window has apparently been used successfully in a number of heritage renovations in inner Sydney and has a lot to offer in terms of thermal, acoustic and security performance, however the planner was doubtful that the solution would immediately satisfy the Council's Heritage consultant. While there is the possibility that, given the time to make detailed presentations, we could get the window approved, we cannot afford to delay the works any further and will direct the builder to patch and repair the existing. Monday, September 13, 2004
Windows
The window fabricator was on site this morning doing a site measure for the windows. At this stage he advises that there may be as much as a 3 week delay before the completed units can be installed, which will significantly delay our construction program. We have asked him to look at ways by which the works can be fast tracked or at least staged to allow the installation of critical windows which in turn will allow the builder to commence internal cladding and fitout works. Friday, September 10, 2004
Material Selection
Spent Thursday and today with the builder at various suppliers checking out plywood sheeting options for the raked ceiling over the upstairs living area and the external cladding. Disappointed to find that one of our previous suppliers is no longer in business. We have decided on a product, finalised our detailed plans accordingly and forwarded these to the builder. Wednesday, September 08, 2004
Integrated wiring 2
RACV's contractor has begun the rough-in of the structured wiring network. We have located the hub in the service cupboard outside the upstairs toilet, above the front bedroom. All data and communications wiring terminates at this control panel allowing maximum flexibility in re programming connections, setting automatic timing functions, adding in additional lines or service connections or changing functionalities. Tuesday, September 07, 2004
Hydronic Heating
Had preliminary discussions with the heating contractor who will be designing and installing the hydronic heating. At this stage we intend to sit the boiler on the platform above the front bedroom, next to the water tanks as long as the exhaust flue can be taken up through the framing to the new roof. We will provide service access to this area via a door through the rear of the storage cupboard in the upstairs guest's vanity. Thursday, September 02, 2004
Design Details
Finalised the design of the courtyard screen with the builder this morning. The wheelie rubbish bin and recycle crate will be concealed from view behind the screen. Though space is tight, we have made allowance for a wheelie recycle bin as well as its likely that the City of Melbourne will follow other municipalities in its introduction. Wednesday, September 01, 2004
Roof Framing 3
Tuesday, August 31, 2004
Roof Framing 2
The top hat sectioned purlins are in place, completing the roof framing steelwork. Delivery of roof sheeting and sarking is expected first thing tomorrow morning. Wednesday, August 25, 2004
Roof Framing 1
Another fine day. Tuesday, August 24, 2004
Damp Proof Repairs
Damp Proof repairs have been completed to the existing original walls at both T1 and T2. It may not look like much, but without the treatment, it would not be too long before the rising damp became obvious. Even with the relatively dry soil conditions under the properties, the original walls were riddled with damp. Monday, August 23, 2004
Water Tank
Wednesday, August 18, 2004
Sliding doors
Another fine day. Tuesday, August 17, 2004
Steelwork 2
Monday, August 16, 2004
Plumbing Rough-in
Friday, August 13, 2004
Steelwork 1
Steelwork delivered to site. The builder had to organise a crane to lift the steel into position - major members are over 14 m long. Access is a problem. The crane could not gain direct access through the rear of the lane and had to work from the laneway intersection two terrace lengths away. It did not have the necessary reach. Wednesday, August 11, 2004
Site Meeting
Good weather today. Monday, August 09, 2004
Steel Fabricator
Prepared additional detailed sections and held detailed discussion with the steel fabricator to explain the roof structure. Experience has shown that this pre-empts possible misunderstandings and incorrect fabricated structural members turning up on site. Friday, August 06, 2004
Engineer's input
Sat down with the engineer today to discuss the roof changes. He is revising the ceiling structure above the front bedroom to take the weight of an in-roof water tank. Spent some time revising the guttering, flashing and downpipe details and discussing plumbing logistics with builder. Tuesday, August 03, 2004
Roof changes
After discussion with the City of Melbourne's environmental consultant, we are investigating the modification of our roof design to be able to collect more roof rainwater. Monday, August 02, 2004
First floor framing
Weather fine. ![]() Cut ridge beam (original) Wednesday, July 28, 2004
Rained out
Heavy rain for most of day. Tuesday, July 27, 2004
First Floor Level
Clear weather day - good for site activity Monday, July 26, 2004
Facade panelling
Spent some time on the phone with various suppliers discussing options for the rear facade panelling. There are probably about 4 alternatives which will give a similar look. Need to consider fixing detailing, availability, durability, sheet size (ease of cutting to size and wastage)and cost. Friday, July 23, 2004
Framing 2
Have complimented builder on the neatness of the site. Its not always easy to keep under control but in the end it makes the whole construction process easier, particularly on such a restricted site as this. Wednesday, July 21, 2004
Framing Begins
Steelwork fixing and framing has commenced, with the steel beams supporting the rear balcony and first floor being fixed in position as well as the timber framing up of internal walls. Friday, July 16, 2004
Drainage
Weather has been good for the last few days with only light drizzle which has not affected the works. Wednesday, July 14, 2004
Building Walls 2
Wall has grown beyond comfortable access height and builder has constructed scaffolding from which to continue block laying. This scaffolding will be raised as the wall continues to grow. Monday, July 12, 2004
Building Walls
Wall is growing. Thursday, July 08, 2004
Blockwork
Clear sunshine today. Wednesday, July 07, 2004
Steel Posts
Cold and wet most of the day. Friday, July 02, 2004
Waiting for slab to cure
Little can be done on site while waiting for the slab to cure. Wednesday, June 30, 2004
Pouring the Slab
Slab poured early morning. Should be smooth and level before noon. Clouds to the south are that deep purple that promises rain. Hope it holds off until later in the day, giving the concrete surface time to harden. Monday, June 28, 2004
Forming Slab
Great morning, overcast afternoon. Very windy all day. Friday, June 25, 2004
Blocklaying begins
Overcast and drizzle clearing up in the afternoon. Wednesday, June 23, 2004
Footings 2
First load of blocks delivered to site this morning. Thursday, June 17, 2004
Footings
After consultation with the engineer, the builder had to take out more of the original structure than we planned. This variation will unfortunately add more to the project cost as he now has to rebuild these walls from the foundations up. Hopefully it won't significantly affect the construction program. Wednesday, June 16, 2004
Sewer Line
The builder is concerned over potential collapse of lane paving at sewer excavation and will provide a weather proof tarp or similar over the excavated area to protect it from rain until the hole can be backfilled. Friday, June 11, 2004
Trenching
Builder beginning excavation of trenches for the laying of sewer lines which will run under the house. These must be laid prior to the pouring of the concrete slab. Will connect to existing sewer line running down the rear laneway. Thursday, June 10, 2004
1866s Jigsaw
Clean up after demolition is a pretty stark reminder of the poor quality construction techniques and materials of mid last century. Our property's walls were founded on a pile of bluestone rubble. The bricks used were unevenly fired with many raw or near-raw doughbough just crumbling away. Brick sizes were uneven with the walls resembling a jigsaw puzzle of bricks laid flat, on edge, fill-in broken ones and thick blobs of mortar to fill in the uneven gaps. We are concerned about the stability and structural integrity of the remaining walls and will need to get the engineer's advice. Wednesday, June 09, 2004
Rain
Melbourne, Beautiful sunshine one day.....continuous rain the next! Tuesday, June 08, 2004
Site Meeting
Met with Builder on site this morning. Lane has been blocked off on our side giving builder better access to site for machinery and equipment. Friday, June 04, 2004
Demolition Day 1
The 1960's extension has been removed. Thursday, June 03, 2004
Waste Removal
Have requested Builder look at ways of reusing demolished materials. Problem here is storage - there is nowhere to clean and keep material on site until they can be reincorporated into the works. Wednesday, June 02, 2004
Building Permit Collected
Builder has picked up Building Permit and is working on demolition strategy in cooperation with the builder of T2. It's a good thing that the two terraces are being constructed at the same time. With the buildings originally built as one, it would have been very difficult to demolish just one side only. Tuesday, June 01, 2004
Project Start
Contract signed. Waiting for 3 day cool off period before Builder can begin on site. |