T1 Architect's Diary
Tuesday, October 26, 2004
Flooring

The lack of windows is resulting in atypical site progress. Applying some lateral thinking, the builder is tackling a number of external items first in order to keep the project moving forward. The water feature pond has been formed. The rear fence, the fence between the two Terraces and the screen fence around the small service 'yard' (more like a corner) are in progress.


Rear water feature - screen to hide
services just beginning on the right


In anticipation of the rain forecast for tonight and tomorrow, the builder has temporarily sealed the building with a combination of sarking foil and boards to protect the internal wall and ceiling linings, as well as the timber flooring which is now being laid.


Temporary weather protection


Rosegum flooring